Building for Every Generation! | 574.773.0603

Certificate of Occupancy Recieved

Great News! The Certificate of Occupancy has been released to all of us, and we are excited to see what you do with the house from this point forward, and we look forward to working with you on many more projects!

Update on Build

Cornerstone is to do outdoor flatwork today. Thornton has completed. Sarah bought insulation for Daniel; it is not yet done due to car issues. Daniel to address egress well being adjusted as well. The concrete dumpster was delivered yesterday.  The excavator is doing...

Final Fit and Finish

The final fit and finish is happening at Taylor St currently, and we are waiting on water to get installed to be able to get the HVAC installed (because of grading). We are going to go as far as we can with fit and finish and the house is looking very good. Will be...

Update 6/19/2023

As of Friday, the 16th, 2023 we have accomplished many things! The rough fit and finish are done. We have addressed the NIPSCO issues; which include the city not updating the address on the permits and/or the inspections – this is the reason for the long delay...

Update 5/30/2023

We have been working hard on getting things done and ready for the next step, the final finish. Unfortunately, we have not heard from the excavator doing the water and sewer work. We look forward to finishing this job as soon as possible.