The Journey Through the Building Process
Overall Job Completion
- Overall Completion 90%
Pre-construction Phase
- First Visit 100%
- Site Visit 100%
- Sales 100%
- Workbooks Created 100%
- Health Permit (Septic and Well Permits) 100%
- Building Permit 100%
- Construction Preview 100%
Utilities
- Electric Application 100%
- Electrical Engineering Meeting 100%
- Natural Gas or Propane Application 100%
- Natural Gas Engineering Meeting 100%
Construction Phase
- Workbooks Review 100%
- Escavation (Hole Dug) 100%
- Footers Poured 100%
- Foundation Poured (Walls) 100%
- Foundation Floor Poured (Garages and Basements Only) 100%
- Sill Plates Installed 100%
- Partial Back Fill 100%
- Egress Windows and Jackposts Ordered 100%
- House Set 100%
- Electrical Installed 100%
- Gas Installed 100%
- HVAC Installed 100%
- Plumbing Finished 100%
- Gutters Installed 100%
- Flatwork (Sidewalks, Porch Caps, and/or Driveway) 100%
- Water and Sewer Line 100%
Fit & Finish
- Marriage Line 100%
- Drywall Repairs 100%
- Fit & Finish 95%
Aftermarket
- 6 Months 100%
- 1 Year 0%
Certificate of Occupancy
- Electrical Inspection 100%
- Mechanical Inspection 100%
- Plumbing Inspection 100%
- Final Inspection 100%
Notes
Certificate of Occupancy Recieved
Great News! The Certificate of Occupancy has been released to all of us, and we are excited to see what you do with the house from this point forward, and we look forward to working with you on many more projects!
Update on Build
Cornerstone is to do outdoor flatwork today. Thornton has completed. Sarah bought insulation for Daniel; it is not yet done due to car issues. Daniel to address egress well being adjusted as well. The concrete dumpster was delivered yesterday. The excavator is doing a contractor grade today. Kenny is rescheduling the water meter today.
Coming down to the end of the house! We are excited to be able to try to get a Certificate of Occupancy and will let you have tenants move in.
Final Fit and Finish
The final fit and finish is happening at Taylor St currently, and we are waiting on water to get installed to be able to get the HVAC installed (because of grading). We are going to go as far as we can with fit and finish and the house is looking very good. Will be updating photos soon!
Update 6/19/2023
As of Friday, the 16th, 2023 we have accomplished many things! The rough fit and finish are done. We have addressed the NIPSCO issues; which include the city not updating the address on the permits and/or the inspections – this is the reason for the long delay on the NIPSCO meter getting installed. Conversations have been had and Catherine has let us know that the water issue is soon to be resolved by Abe’s Plumbing. Once the water is on we will be able to finish the house completely, and we will be able to have a walkthrough with everyone! New photos of the progress of the fit and finish have been uploaded along with the ability to see the latest photos first…
Please let any of us know if there are any issues. We will work to make sure that these are fixed immediately; within what is in our control.
Update 5/30/2023
We have been working hard on getting things done and ready for the next step, the final finish.
Unfortunately, we have not heard from the excavator doing the water and sewer work.
We look forward to finishing this job as soon as possible.
Update on the Street
- Catherine Pingle is meeting with the South Bend Committee sometime this week (10/10/2022 – 10/14/2022) to figure that all out.
- The gutters are done but will have to be done around the porch once Jesse completes the porch. We are waiting on the gas line to be completed for NIPSCO.
- Power will be on soon, we are within the 10 days.
Waiting on NIPSCO Engineer
Gas meter placement is hinging on where a NIPSCO engineer will allow us to put it. Kenny contacted NIPSCO Engineer Robert Eberle to get contact information for DTSB Engineer. It was reported that Dustin Walker was the engineer for DTSB and will be going on vacation starting 8/31/2022 for two weeks and that Robert would help get the lateral locations involved in order to get our stub-outs ready for gas meter installation.
House Set
The house for the Affordable Housing Committee in South Bend was set on 8/25/2022. Kenny dropped off the egress window on 8/29/2022 around 13:00.